Timeline - initial

May 2018 – June 2018

Project documentation:

  • project overview
  • expense list
  • project timeline
  • possible collaborations with companies, laboratories and student associations

Finances:

  • preparation of applications for funds

July 2018

Application for funds, contacting possible partners, project promotion (among students – LARES web, associations etc.)

August 2018

SUMMER!

September 2018 – October 2018

Procurement of equipment, greenhouse building

October 2018 – November 2018

Connecting of sensors, actuators, panels with raspberry PI, promotion within Imagine, Create, Innovate closing

September 2018 – February 2019

Database setup, data collecting, initial models identifications, control systems development

March 2019 – August 2019

Control systems implementation and testing, first plant seedlings included